Roll-out of full fibre broadband in the UK
This ICE insights paper examines the roll-out programme for full-fibre and gigabit-capable broadband. It considers the potential economic and social benefits, delivery challenges and the potential for alternative approaches. |
Contents |
[edit] Introduction
A major infrastructure programme – the installation of full-fibre and gigabit-capable broadband to every home and business across the UK – is planned to be near complete.
As ICE’s new insights paper on the rollout of full-fibre broadband reveals, this is an incredibly ambitious target. When the Future Telecoms Infrastructure Review was released in 2018, the then Government under Theresa May aimed to ensure a full-fibre-to-the-premises (FTTP) network would be in place by 2033. The new target – of 2025 – is a full eight years earlier than planned just two years ago.
[edit] The engineering challenges
A new fibre-optic network is capable of delivering much faster upload and download speeds for households and businesses. Without it, next generation technology, including mobile 5G, will struggle to perform. Fibre is also more reliable than existing copper cables, with performance more resilient to weather or electromagnetic interference.
Installing it to every home and business is first and foremost a massive engineering challenge. It will mean new trenches dug into many residential streets in the UK and new ducts and poles crisscrossing – and connecting – the nation.
[edit] Enabling a digital economy
A full-fibre network would have wide-ranging economic impacts. Openreach believes it will boost the economy by some £60 billion by 2025, enabling some people not in the workforce to re-enter work, and support more people to work remotely. This economic and speed stimulus is desperately needed in a world which is more interconnected. While the UK has an impressive 95% coverage for super-fast broadband, just 8% of the country is covered by fibre connectivity. When 28% of France, 71% of Spain and 97% of Japan has access to fibre-enabled broadband, Britain is at risk of falling far behind in the global race.
Fibre does not just add speed – it also adds capacity. As the country grows, as technology develops and as more information flows, it is important to avoid bottlenecks. Full-fibre would also have a profound impact on economic infrastructure. Building Information Modelling, digital twins and remote monitoring will all benefit from increased speed, connectivity and reliability. Tomorrow’s engineers will design, build, collaborate and improve infrastructure assets in real time, from anywhere in the world.
[edit] Are there better ways to connect the UK?
ICE’s paper also examines alternative pathways for delivering enhanced Internet connectivity. These include Canada’s plans to link up its communities using low earth orbit satellites and how 5G could be leveraged to better connect homes to the fibre network.
Readers can view ICE’s Insight paper here – Civil engineering insights on the rollout of full-fibre broadband and alternative proposals.
[edit] About this article
This article was written by ice.org.uk Ben Goodwin, Lead Policy Manager at the Institution of Civil Engineers (ICE). It previously appeared on the ICE website in January 2020 under the title 'Civil engineering insights into the roll-out of full-fibre broadband in the UK' and can be accessed HERE.
Other articles by the ICE on Designing Buildings Wiki can be accessed HERE.
[edit] Related articles on Designing Buildings
- Broadband universal service obligation (USO).
- Designing smart cities.
- Digital Built Britain.
- Electrotechnical industry gears up for All-IP switch.
- How to make the digital revolution a success.
- Information and communications technology.
- Rural.
- Rural productivity plan.
- UK Digital Strategy.
- Vital infrastructure and redevelopment.
Featured articles and news
HBPT and BEAMS Jubilees. Book review.
Does the first Labour budget deliver for the built environment?
What does the UK Budget mean for electrical contractors?
Mixed response as business pays, are there silver linings?
A brownfield housing boost for Liverpool
A 56 million investment from Homes England now approved.
Fostering a future-ready workforce through collaboration
Collaborative Futures: Competence, Capability and Capacity, published and available for download.
Considerate Constructors Scheme acquires Building A Safer Future
Acquisition defines a new era for safety in construction.
AT Awards evening 2024; the winners and finalists
Recognising professionals with outstanding achievements.
Reactions to the Autumn Budget announcement
And key elements of the quoted budget to rebuild Britain.
Chancellor of the Exchequer delivers Budget
Repairing, fixing, rebuilding, protecting and strengthening.
Expectation management in building design
Interest, management, occupant satisfaction and the performance gap.
Connecting conservation research and practice with IHBC
State of the art heritage research & practice and guidance.
Innovative Silica Safety Toolkit
Receives funding boost in memory of construction visionary.
Gentle density and the current context of planning changes
How should designers deliver it now as it appears in NPPF.
Sustainable Futures. Redefining Retrofit for Net Zero Living
More speakers confirmed for BSRIA Briefing 2024.
Making the most of urban land: Brownfield Passports
Policy paper in brief with industry responses welcomed.
The boundaries and networks of the Magonsæte.